Great Lakes the low bidder for 2022 Avon/Buxton beach nourishment project

Work on the Buxton beach nourishment project in June 2017. [photo courtesy Cape Hatteras Motel]

Dare County has received bids for the Avon and Buxton beach nourishment projects from Great Lakes Dredge and Dock Co., Manson Construction and Weeks Marine.

The low bidder was Great Lakes Dock and Dredge Co. at $25,870,000 with a start date of May 1, 2022, and an end date of September 30, 2022. The Avon and Buxton beach nourishment project’s estimated cost is $30,211,176.

The bids were opened on November 17. However, the proposals must still be evaluated for completeness before a specific bid can be recommended to the Dare County Board of Commissioners, which will then give approval to award the bid.

Great Lakes Dock and Dredge most recently conducted the beach widening projects from Duck to Nags Head four years ago.

To view the Avon and Buxton beach nourishment tabulation, click here.

Dare County will use occupancy tax and property tax funds to pay for the Avon project, a first for the beach stretching from Due East Road to the Ramp 38 area.

The sand lost from previous beach widening from the Haulover to the old Coast Guard base in Buxton, and South Nags Head from Jennette’s Pier to the Cape Hatteras National Seashore border, was determined to have been caused by recent hurricanes, making the projects eligible for federal and state disaster relief funds.

An announcement about the bids for the South Nags Head project are pending.

Weeks Marine submitted a bid of $27,932,050 for the sand pumping projects that are anticipated to take place next spring and summer off Duck, Southern Shores, Kitty Hawk and Kill Devil Hills.

The same company ran into numerous mechanical and weather delays while widening the beaches off Buxton between 2017 and 2018.

A combination of funding for those projects will come from funds set aside for beach nourishment from the county’s occupancy tax on hotel/motel room and vacation property rentals, along with a portion of property taxes assessed in the four towns that have been designated to beach nourishment.

Duck, Southern Shores, Kitty Hawk and Kill Devil Hills will have to come up with just under $12 million combined, while the county’s beach nourishment fund contribution will be just over $8.7 million, and there are grants of $11.7 million from FEMA and the state.

Exact dates for next year’s nourishment projects have not been set, so it is still too early to know when workers and equipment will be along a specific section of Outer Banks beach.

More information about beach nourishment on the Outer Banks can be found at MoreBeachToLove.com